In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

a primary goal of the Monroe Doctrine (1823) was to
The purpose of critical reading is to____________a text. a. Preread c. Evaluate b. Questions d. None of these
combine like terms to simplify the expression 2/5k-3/5k+1/10k
Egypts first pharaoh
To Build a Fire: Read the sentences from the passage. “He plunged in among the big spruce trees. The trail was faint. A foot of snow had fallen since the last s
what was parliament's reasoning for taxing the colonists at that time
Why does hot air rise and cold air sink??
Find the Nth term of the following sequence... 7, 27, 47, 67, .....
Suppose you are assigned two unknowns, Compound A and Compound B. One unknown is a fat, while the other is an oil. You dissolve a small amount of Compound A in
If the sphere shown above has a radius of 6 units, then what is the approximate volume of the sphere? A. 1,130.4 cubic units B. 452.16 cubic units C. 9