Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

how are solutions and compounds similar
ammar hikes 23/4 miles of nature trail in 1 hour and 15 min .How many miles of trail does ammar hike per hour? pleas help me to understand this
During digestion, why do you think it is necessary to break up the fat into tiny droplets?
what does a trapezium look like
toussaint L'Overtture led a revolt that eventually resulted in independence for what country
Why might the iodine change color when it combines with starch?
During digestion, why do you think it is necessary to break up the fat into tiny droplets?
In addition to replacing the president if necessary, it's the duty of the vice president to
five times a number minus 12 is 92. what is  the number
After mrs.fisher lost 17% of her invetment, she had $10375 How much did she had initially?